Palm Jebel Ali – phase 1, Dubai, United Arab Emirates2023-08-30T09:42:26+02:00

Project Description

Context of the project

The Palm Jebel Ali’ is the second in the series of three “palm trees” that form an archipelago of artificial islands reclaimed from the sea in Dubai and set out in the shape of a palm tree. This Palm is intended to house residential and tourist complexes, shopping and leisure centres, for a population of approximately 250,000 people.

Description of the project

The Vibroflotation Group Ltd, a former Soletanche Bachy subsidiary, as part of a joint venture with APCC, was awarded the design and build contract for ground improvement works.

The site covers 10km2 of land to be treated, spread over a total area measuring 50km2, where most access to the work sites is by sea. This non-standard site mobilized more than 400 people with up to 20 cranes and a series of 36 compaction units (V48 for compacting and V23 for the stone columns).

Our solution

After backfilling an area contained by rock armour to a thickness of approximately 15m, vibroflotation treatment could commence. This technique, sometimes called vibrocompaction, is used to increase load-bearing capacity, homogenise soil conditions, limit subsidence and differential settlement and eliminate the risk of liquefaction in granular soils. Once this treatment was completed, 60 load-bearing tests, 1,000 test bores and 40,000 CPT (Cone Penetration Tests) were carried out.

Works performed:

  • 170,000,000m3 of backfill
  • 10,000,000 tonnes of rocks for the dykes
  • 10,000,000m2 of land created
  • 70km of beaches
  • Project total surface area: 49km2

The Ressources:

  • 16 cranes in service
  • 24 x 500KVA to 1,250KVA generating sets
  • 38 compressors
  • 50 compaction units
  • 18 mechanical loaders
  • 2 unloading lighters
  • 5 fast transport vessels

Type of project:

Buildings and housing

Buildings and housing

Location:

United Arab Emirates

Project owner:

NAKHEEL

Prime contractor:

China Railway Engineering Me

Consortium:

APCC – VFL joint-venture

Types of techniques:

Ground improvement

Ground improvement

Key figures of the project

0
nationalities present on the project and 10 working languages
0
of land worked per day
0m3
of land treated per day
0
dynamic cone penetrometer measurements carried out and analysed each week