{"id":10234,"date":"2021-09-10T14:00:05","date_gmt":"2021-09-10T12:00:05","guid":{"rendered":"https:\/\/www.soletanche-bachy.com\/?p=10234"},"modified":"2022-12-01T14:16:18","modified_gmt":"2022-12-01T13:16:18","slug":"soletanche-bachy-france-has-completed-a-new-operation-on-rer-line-c","status":"publish","type":"post","link":"https:\/\/www.soletanche-bachy.com\/en\/soletanche-bachy-france-has-completed-a-new-operation-on-rer-line-c\/","title":{"rendered":"Soletanche Bachy France has completed a new operation on RER line C"},"content":{"rendered":"
September 10th, 2021<\/p>\n<\/div>
The 24th Castor works campaign is coming to an end! Following cancellation in 2020 on health grounds, the drills returned to the RER C tunnel this year to strengthen the 135m of tunnel out of Invalides station.<\/strong><\/p>\n<\/div>